Earned Value#
Planned Value The total budgeted cost up to the analysis date.
Earned Value Calculated for the task using the following formula:
Earned Value = Current Budget x Physical Percent Complete
If the physical percent complete rollup method for the workplan is Effort, then earned value is based on effort. Otherwise, earned value is based on cost. Depending on the hysical percent complete rollup method, Oracle Projects uses either the baseline planned effort or cost for the task to determine the Current Budget.
Schedule Performance Index
Calculated for the task using the following formula:
Schedule Performance Index = Earned Value / Planned Value
Cost Performance Index
Calculated for the task using the following formula:
Cost Performance Index = Earned Value / Actual Cost
If the values are null, after running the project performance reporting requests(jobs) looks like Earned value is not getting calculated, cross check the budgets, physical percent complete complete rollup method for the workplan
Planned Value The total budgeted cost up to the analysis date.
Earned Value Calculated for the task using the following formula:
Earned Value = Current Budget x Physical Percent Complete
If the physical percent complete rollup method for the workplan is Effort, then earned value is based on effort. Otherwise, earned value is based on cost. Depending on the hysical percent complete rollup method, Oracle Projects uses either the baseline planned effort or cost for the task to determine the Current Budget.
Schedule Performance Index
Calculated for the task using the following formula:
Schedule Performance Index = Earned Value / Planned Value
Cost Performance Index
Calculated for the task using the following formula:
Cost Performance Index = Earned Value / Actual Cost
If the values are null, after running the project performance reporting requests(jobs) looks like Earned value is not getting calculated, cross check the budgets, physical percent complete complete rollup method for the workplan